Supertech's ambitious project, Noida Twin Towers, rose and fell between 2004 and 2022.
The structure taller than the Qutub Minar would be brought down with explosives weighing at least 3,700 kilograms. Supertech's ambitious project, Noida Twin Towers, rose and fell between 2004 and 2022. Updated: 28 Aug 2022, 10:07 AM IST
Noida twin towers: 3700 kg explosives will bring the two massive structures down at 2:30 pm today, creating whopping 80000 tonnes of debris.
The High Court ordered the Twin Towers to be destroyed in 2014. As a result of the purchasers' persistence, the Supreme Court maintained the Allahabad High Court's verdict and mandated its demolition no later than November 2021. In this case, the Supreme Court had harsh words for the top brass of Noida Authority. Later, the matter was taken to the Allahabad High Court. The main problem was that this construction was built in violation of the law. A judicial battle was fought ffrom Allahabad High Court to the Supreme Court but the Supertech Builder's outstanding lawyers couldn't save the firm from loosing the case.
The Supertech twin towers in Noida, which are taller than the Qutub Minar, will be razed to the ground at 2:30 pm today, nine years after residents went to ...
The Supreme Court observed that building norms were violated by the builder in collusion with Noida authorities. Last August, the court gave three months to demolish the towers, but it's taken a year due to technical difficulties. The petitioners argued that the Supertech group violated norms to sell more flats and enhance their profit margins.
Noida Twin Tower Demolition: In both cases, construction was carried out by builders in collusion with local authorities.
Residents in the However, in the Maradu case, the towers had been completed and were even occupied by residents. In both cases, the Supreme Court had declined to regularise the unauthorised construction. The complexes housing a total of 343 flats were brought down using the implosion method. For the demolition of the Alpha Serene building (one of the four Maradu buildings), demolition experts had to ensure that the adjoining water body did not get polluted and that minimum debris went into the water. The 103-metre Supertech Twin Towers in Noida will be demolished at 2.30 pm on August 28.
The stage is set for the Noida twin tower demolition and people are evacuating the area already. The evacuation of around 5,000 residents of Emerald Court ...
The demolition of the two illegally built towers is scheduled for 2.30 pm. The closest buildings next to twin towers are Aster 2 and Aster 3 of Emerald Court society which are just nine metres away. The Noida Authority has also set up a control room which will register complaints to deal with any emergency after the building collapse. Officials are conducting drills with ambulances in preparation of the demolition, sources said. The structures, deemed unlawfully constructed by the Supreme Court, will be demolished at 2:30 pm on August 28, Sunday. The Supreme Court had on August 12 allowed an extended deadline of August 28 with a bandwidth of seven days until September 4 to demolish the 103-metre-tall twin towers โ Apex and Ceyanne. Long-term benefits of demolition will be seen in 3 months: UBS Teotia, RWA Pres, Emerald Court & petitioner in Twin Towers case, on demolition of However, the fixing of explosives was started from August 13 with a vision to maintain the previous deadline. โWinds will blow from NW on Sunday August 28, at the time of Twin Tower Demolition. A team of engineers have arrived at the demolition spot while a control room has also been set up. Today the building of corruption of SP will collapse in the BJP government under the leadership of Chief Minister Shri Yogi Adityanath ji. The stage is set for the Noida twin tower demolition and people are evacuating the area already.
India's tallest building, the Twin Towers in Supertech's Emerald Project, Sector 93A of Noida will be razed to the ground on Sunday, August 28.
For building heights up to 18 meters, the distance should be 6 metre and spacing shall be increased by 1 metre for every addition of 3 metres, as per National Building Code 2005." In 2009, the plan was re-revised to include the twin high-rise buildings โ Apex and Ceyane. While it will only take 9 seconds, with explosive connections on each of the floors of the Ceyane (29 floors) and Apex (32 floors), it will lead to a loss of about Rs 1,000 crore to developer Supertech.
Cooking gas and power supply lines have also been discontinued in the two societies in Sector 93A.
Follow us on [also read] [India](https://www.firstpost.com/category/india) [Noida: Illegal Supertech twin towers 'charged' with 3,700 kg of explosives; demolition to take place on 28 August](https://www.firstpost.com/india/noida-illegal-supertech-twin-towers-charged-with-3700-kg-of-explosives-demolition-to-take-place-on-28-august-11098591.html) The twin towers are set to be razed over grave violations of building norms. The placing of explosives was completed on Monday evening and the next procedure, known as trunking, will start today. The exercise was earlier supposed to start on 21 August but the court accepted the Noida Authorityโs request and extended its date of demolition to 28 August. Also, one ACLS ambulance equipped with all the necessary medications and equipment will be on standby for any mishappening," said a statement issued by the Jaypee Hospitals which are nearest to the area where the demolition will take place. The towers are expected to be brought down in less than 15 seconds by waterfall implosion technique. The flick of this switch will turn the towers into a pile of rubble in a matter of seconds, says Edifice Engineering. About 25,000 tonnes of the debris will have to be scientifically disposed of in three months. A puja was performed by the demolition crew at the blast site just a while ago. The air space in one nautical mile radius above the blast zone will also remain briefly unavailable for flights during demolition time, according to the Noida Authority. The demolition would be done in a manner so as not to cause any structural damage to other buildings, they said. Supertech states that they are committed to give delivery to remaining homebuyers as per the scheduled time frame.
Noida Supertrech Twin Tower Demolition Live Updates: The buildings, that are scheduled to be razed at 2.30 pm today, compelled 5000 residents of Emerald ...
Only last minute inspections remain as the towers -- taller than Delhi's iconic Qutub Minar -- will be brought down in less than 15 seconds by waterfall implosion technique. Around 5,000 residents of Emerald Court and adjoining ATS Village societies in Sector 93A have to vacate their premises by 7 am on Sunday while also removing nearly 3,000 vehicles and taking away 150-200 pets, including cats and dogs, with them for the day. The closest buildings next to twin towers are Aster 2 and Aster 3 of Emerald Court society which are just nine metres away. The air space in one nautical mile radius above the blast will also remain briefly unavailable for flights during demolition time, according to Noida Authority. All work related to placement of explosives and connecting them is already complete. We have today saved almost 30-35 dogs, we're working on getting out each & every one of them: NGO member. It will be opened half an hour after blast, soon as dust settles down. Expressway only to be closed right before the blast at around 2.15pm. It will be opened half an hour after the blast, as soon as dust settles down. Residents of two housing societies near Noida's Supertech twin towers evacuated. Two drummers have been called outside the Parsvnath Society to play the drums during the demolition exercise. Long-term benefits of demolition will be seen in 3 months: UBS Teotia, RWA Pres, Emerald Court & petitioner in Twin Towers case, on demolition of